Master resource allocation, optimization, and management strategies
Managing Project Resources is the process of ensuring that the physical resources assigned and allocated to the project are available as planned, as well as monitoring the planned versus actual utilization of resources and taking corrective action as necessary.
Purpose: Smooth out resource demand over time
Method: Delay activities to avoid resource over-allocation
Impact: May extend project duration
Use when: Resources are limited and cannot be increased
Purpose: Adjust activities within float to smooth resource usage
Method: Move activities within available float
Impact: Does NOT change critical path or project duration
Use when: You want to optimize resource usage without changing end date
Technique | Method | Cost Impact | Risk Impact | Best Used When |
---|---|---|---|---|
Crashing | Add resources to critical path | Increases cost | Moderate risk | Budget available, resources can be added |
Fast Tracking | Do activities in parallel | May increase cost | Increases risk | Activities can be done simultaneously |
Utilization = (Actual Hours Worked / Available Hours) ร 100%
Efficiency = (Planned Hours / Actual Hours) ร 100%
Productivity = Work Output / Resource Input
The project schedule shows that electrical engineers are over-allocated during weeks 3-5. The project end date cannot change. What should the project manager do?
A) Use resource leveling to smooth the allocation
B) Use resource smoothing to adjust within float
C) Crash the schedule by adding more engineers
D) Fast track the electrical activities
Answer: B - Resource smoothing works within float and doesn't change end date
To reduce project duration, the project manager decides to perform testing activities in parallel with development activities. This is an example of:
A) Resource leveling
B) Resource smoothing
C) Crashing
D) Fast tracking
Answer: D - Fast tracking involves doing activities in parallel
A critical path activity needs 100 hours and costs $50/hour. It can be crashed by adding resources to complete in 80 hours at $60/hour. What is the crash cost per hour saved?
A) $10
B) $50
C) $60
D) $85
Answer: D - Crash cost = (80ร$60 - 100ร$50) รท (100-80) = $1700 รท 20 = $85
Resource utilization shows 120% allocation for the development team. The project manager should:
A) Continue as planned since the team is highly productive
B) Immediately implement resource leveling
C) Add more resources to the team
D) Fast track other activities to balance the load
Answer: B - 120% allocation indicates over-allocation requiring leveling